"Scope of Judicial Interference under the Arbitration and Conciliation Act: An Analysis of the 2025 INSC 574 Ruling"





                                                                                                       

Authored By: Dr.Vandita Chahar (Asst. Professor ) , Jaipur National University , Jaipur

Subject: Arbitration Law – Judicial Scope under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996; Contract Law – Liquidated Damages and Extension of Time

Case Title: Consolidated Construction Consortium Ltd. v. Software Technology Parks of India

Judges: Justice Abhay S. Oka and Justice Ujjal Bhuyan

Date: April 28, 2025

Citation :( 2025) INSC 574

Court: Supreme Court of India

Case Number: Civil Appeal No. 5383 of 2024

Parties:

  • Appellant: Consolidated Construction Consortium Limited
  • Respondent: Software Technology Parks of India


----------------------------------------------------------------------------------------------------------------------------

Facts:

  • The Software Technology Parks of India (Respondent) awarded a construction contract to Consolidated Construction Consortium Limited (Appellant).
  • As per the contract, the scheduled date for completion of construction was 15.01.2007.
  • However, the Appellant completed the construction only on 30.11.2007, resulting in a delay of approximately 10 months.
  • Invoking Clause 26 of the contract, the Respondent levied and deducted ₹82,43,499 as liquidated damages for the delay.
  • The Appellant invoked arbitration proceedings challenging the deduction and other claims.
  • The Arbitral Tribunal upheld the Respondent’s deduction of liquidated damages, finding it legally and contractually valid.
  • Aggrieved, the Appellant filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 before the High Court seeking to set aside the arbitral award.
  • A Single Judge of the High Court allowed the petition, holding that the extension of time granted for completion negated the basis for deduction of liquidated damages.
  • The Respondent challenged the Single Judge’s order by way of an appeal under Section 37 of the Arbitration Act.
  • The Division Bench of the High Court allowed the appeal, setting aside the Single Judge's judgment and restoring the arbitral award.
  • Dissatisfied, the Appellant approached the Supreme Court by way of Special Leave Petition.

Issues:

  • Whether the Division Bench of the High Court was justified in setting aside the Single Judge’s order and restoring the arbitral award under Section 37 of the 1996 Act.

Arguments

Appellant's Arguments:

The Appellant, Consolidated Construction Consortium Limited, raised several substantive objections to the judgment of the Division Bench, primarily contending that the High Court exceeded the scope of its jurisdiction under Section 37 of the Arbitration and Conciliation Act, 1996 ("1996 Act"). It was argued that the Division Bench effectively undertook a merits review of the arbitral award, a process akin to an appellate exercise, which is explicitly barred under the limited framework of Sections 34 and 37 of the 1996 Act. According to the Appellant, interference by the Division Bench was unwarranted because appellate courts under Section 37 are confined to examining whether the court under Section 34 correctly applied the narrow grounds of interference, and not to reappraise facts or substitute their interpretation.

The Appellant further contended that levy of liquidated damages was unjustified once extension of time for completion of the contract had been granted by the Respondent. It was submitted that when an employer extends the time for performance without reservation or re-negotiation of contractual terms, the right to impose liquidated damages for the delayed period stands waived or is rendered legally untenable. The Appellant placed reliance on principles governing construction contracts, emphasizing that time is not of the essence in construction projects unless expressly stipulated and rigidly enforced. Reference was made to Sections 55, 73, and 74 of the Indian Contract Act, 1872, to argue that in absence of a demonstrable loss or express reservation, levy of liquidated damages was unsustainable.

It was further argued that the Respondent’s conduct, including the repeated extensions of time without contemporaneous claims for damages and the acceptance of work performed beyond initial deadlines, constituted waiver of the right to impose liquidated damages. The Appellant submitted that the post-facto issuance of extension letters and the failure to issue prior notices of intent to levy damages further reinforced that the Respondent had accepted the delayed performance without qualification.

Additionally, the Appellant asserted that the Arbitral Tribunal failed to appreciate that no actual loss had been suffered by the Respondent, a critical requirement under Indian contract law for enforcing even a pre-determined amount of compensation. Hence, the award upholding the deduction of liquidated damages was liable to be set aside.

Respondent's Arguments:

Conversely, the Respondent, Software Technology Parks of India, vehemently defended the decision of the Division Bench, asserting that the Single Judge had exceeded the scope of Section 34 by reappreciating evidence and reinterpreting contractual clauses. It was submitted that the Division Bench merely restored the arbitral award after correctly finding that the Single Judge’s interference was beyond the permissible grounds under Sections 34(2) and 34(2A).

The Respondent emphasized that time was expressly made the essence of the contract, considering the commercial nature of the project and the adverse financial consequences of delay. The Respondent pointed to multiple review meetings, extension letters, and correspondence wherein it was consistently made clear that any extension of time was granted "without prejudice" to its right to levy liquidated damages. Thus, there was no waiver or abandonment of rights by the Respondent, and the Appellant was continuously on notice regarding the potential imposition of damages for delayed completion.

Additionally, the Respondent contended that substantial actual losses were incurred due to the delay, specifically:

  • Continued payment of rent for the previous premises while awaiting completion of the new office complex.
  • Loss of rental income from the newly constructed premises for the period of delay.

These losses were evidenced and quantified before the Arbitral Tribunal, which after due consideration found the Respondent’s claims to be valid and reasonable. The Respondent further argued that Clause 26 of the contract specifically authorized the imposition of liquidated damages in the event of delay, and the quantum levied (0.5% per week of delay) was contractually stipulated and proportionate.

The Respondent thus urged that the arbitral award, being a plausible interpretation based on contractual terms and factual findings, was entitled to judicial deference. Reliance was placed on the established principle that courts should not reappreciate evidence or substitute their view for that of the arbitrator, especially when the arbitrator’s view was a possible and reasonable one.

Accordingly, the Respondent submitted that the Division Bench rightly reversed the Single Judge's overreach and restored the sanctity of the arbitral process, thereby aligning with the objectives of minimal judicial intervention under the 1996 Act.

Legal Issue

The primary legal issue before the Supreme Court was:

Whether the Division Bench of the High Court was justified, under Section 37 of the Arbitration and Conciliation Act, 1996, in setting aside the Single Judge’s order under Section 34, thereby restoring the arbitral award upholding the deduction of liquidated damages, despite extensions of time having been granted for completion of the contract.

Closely tied to this central question were the following sub-issues:

  • Whether an extension of time for performance of a construction contract automatically nullifies the employer’s right to levy liquidated damages.
  • Whether the Single Judge, in setting aside the arbitral award, exceeded the permissible limits of judicial interference prescribed under Section 34 of the 1996 Act.
  • The extent to which a court under Section 34 may reappreciate evidence or reinterpret contractual terms when examining an arbitral award.
  • Whether the Division Bench, acting under Section 37, properly confined itself to assessing jurisdictional overreach rather than conducting a merits review of the dispute.

Supreme Court’s Holding

The Supreme Court unanimously dismissed the appeal and upheld the Division Bench’s decision to restore the arbitral award, making several important observations:

  • The Single Judge exceeded the jurisdiction conferred by Section 34 of the Arbitration and Conciliation Act, 1996, by engaging in reappreciation of evidence and reinterpretation of contractual clauses.
  • Extension of time for contract performance does not, by itself, extinguish the employer’s right to levy liquidated damages, particularly where extensions were expressly granted without prejudice to that right, and where the employer reserved its entitlement in written communications.
  • The Arbitral Tribunal’s findings that the deduction of ₹82,43,499 as liquidated damages was contractually valid, proportionate, and reasonable were held to be a plausible view, warranting judicial deference even if an alternative interpretation could be conceived.
  • The scope of judicial interference with arbitral awards under Sections 34 and 37 is extremely narrow. Courts must resist the temptation to reassess merits or substitute their own views for those of the arbitral tribunal.
  • Proceedings under Section 34 are summary in nature, and Section 37 appellate review is confined to assessing whether the Section 34 court correctly applied the limited statutory grounds for setting aside an award.
  • Arbitral autonomy must be respected. Excessive judicial interference would defeat the legislative intent behind the Arbitration and Conciliation Act, 1996, which seeks to promote arbitration as a final and binding dispute resolution mechanism.

In conclusion, the Court affirmed that minimal intervention, respect for arbitral findings, and strict adherence to the statutory grounds for setting aside awards remain the bedrock principles governing post-award judicial review in India.

Reasoning of the Supreme Court

The Supreme Court engaged in a meticulous examination of the statutory framework, arbitral jurisprudence, contractual interpretation, and the factual matrix of the case. Its reasoning unfolded across several critical axes:

1. Scope and Nature of Section 34 Proceedings

The Court underscored that Section 34 of the Arbitration and Conciliation Act, 1996 is not an appellate provision. It permits judicial interference with an arbitral award only on very narrowly defined grounds, namely:

  • Lack of jurisdiction,
  • Procedural irregularities,
  • Violation of public policy,
  • Patent illegality on the face of the award (for domestic awards).

Importantly, the Court stressed that a judicial authority under Section 34 is not empowered to reappraise evidence or correct errors of fact or law, unless those errors fall within the specific statutory grounds. In this case, the Single Judge had reinterpreted contractual clauses and re-evaluated factual findings of the Arbitral Tribunal without demonstrating how the award contravened any provision under Section 34(2) or 34(2A). This amounted to an impermissible merits review, thereby vitiating the Single Judge’s order.

Thus, the Division Bench, while exercising limited appellate power under Section 37, correctly identified that the Single Judge’s order was without jurisdiction and accordingly restored the arbitral award.

2. Deference to Arbitral Tribunal’s Interpretation

The Court reaffirmed that when an arbitrator adopts a plausible and reasonable view, even if two interpretations are possible, the court cannot substitute its own interpretation for that of the arbitral tribunal. In the instant case, the tribunal, after considering extensive evidence and contract terms, held that the levy of liquidated damages under Clause 26 was valid, reasonable, and proportionate.

Thus, the Supreme Court concluded that the Arbitral Tribunal’s findings could not be disturbed merely because the court could have construed the contract differently. Judicial deference is warranted where the arbitrator’s view is not perverse or irrational.

3. Impact of Extension of Time on Liquidated Damages

The appellant had contended that extension of time nullified the right to levy liquidated damages. However, the Supreme Court held that:

  • Extensions of time were repeatedly granted with explicit reservations by the Respondent that such extensions were "without prejudice" to its right to claim liquidated damages.
  • Therefore, no implied waiver or abandonment of the right occurred.
  • The Respondent’s continuous notifications and communications placed the Appellant on clear notice regarding potential liability for delay.

The Court observed that mere grant of extension, in the absence of clear intention to waive rights, does not destroy the employer’s entitlement to liquidated damages, especially where actual prejudice (loss of rental income, continued payment of rent elsewhere) was demonstrated.

4. Requirement of Actual Loss in Liquidated Damages Claims

The Supreme Court acknowledged that under Section 74 of the Indian Contract Act, 1872, reasonable compensation is payable for breach, irrespective of actual loss being strictly proved. However, in the present case, the Arbitral Tribunal had in fact found evidence of genuine loss — namely:

  • The cost of continuing rent payments for old premises.
  • Loss of rental income from the new premises.

Thus, the award was not only legally sound but also factually substantiated, eliminating any contention that the deduction was arbitrary or punitive.

5. Minimal Judicial Interference and Summary Nature of Section 34

The Court reaffirmed that Section 34 proceedings are summary in nature, requiring courts to confine their review to the "four corners" of Section 34 grounds. Courts must resist reopening the entire arbitral record or undertaking a fresh factual adjudication. Judicial minimalism, the Court stressed, is critical to maintaining the efficacy, finality, and purpose of arbitration as a dispute resolution mechanism.

Key Legal Principles Reaffirmed

From the above reasoning, the following foundational legal principles were explicitly reaffirmed:

1. Limited Scope of Review under Section 34

The power to set aside an arbitral award is strictly confined to grounds enumerated under Section 34(2) and (2A). Mere errors in the interpretation of law, erroneous appreciation of evidence, or possible alternative interpretations do not provide a basis for interference.

Authority Cited:Associate Builders v. DDA, (2015) 3 SCC 49.

2. No Reappreciation of Evidence

A court cannot reappreciate facts or substitute its own interpretation merely because another view is possible. The Arbitral Tribunal’s findings must be respected if they are:

  • Plausible,
  • Based on evidence, and
  • Not perverse or irrational.

Authority Cited:ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705; Ssangyong Engineering v. NHAI, (2019) 15 SCC 131.

3. Respect for Arbitral Autonomy

The autonomy and finality of arbitral proceedings are the cornerstones of the 1996 Act. Courts must interfere only in exceptional cases where statutory thresholds for invalidity are met.

Authority Cited:Project Director, NHAI v. M. Hakeem, (2021) 9 SCC 1.

4. Extension of Time Does Not Extinguish Right to Damages

An employer's right to recover liquidated damages remains intact despite granting an extension of time, provided such extensions are expressly or impliedly made without prejudice to the right to damages.

Principle: Consistent with Section 55, Indian Contract Act, 1872.

5. Reasonable Compensation Under Section 74, Indian Contract Act

Even where actual loss is not proved with precision, parties are entitled to reasonable compensation if stipulated liquidated damages are a genuine pre-estimate of loss. Proof of some loss strengthens the validity of the claim.

Authority Cited:ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705.

6. Summary Nature of Section 34 Proceedings

Section 34 proceedings are intended to be swift and narrowly focused. They are not substitutes for full trials or appeals and are designed to uphold, not unsettle, arbitral awards.

Policy Principle: Preservation of the speed, efficiency, and finality of arbitration.

Critical Commentary

The Supreme Court’s decision in Consolidated Construction Consortium Ltd. v. Software Technology Parks of India is a reaffirmation of the judiciary's increasingly deferential stance toward arbitral awards. While the judgment aligns with the pro-arbitration posture of the Arbitration and Conciliation Act, 1996 (especially post-2015 amendments), it also invites nuanced scrutiny regarding the balance between arbitral finality and judicial oversight in cases involving public interest, contractual ambiguity, or asymmetry in bargaining power.

I. Reasserting Judicial Minimalism: A Necessary Correction?

The Court’s insistence that the Single Judge exceeded the jurisdictional boundaries under Section 34 is doctrinally sound. Section 34, by design, is a non-appellate, narrow remedy — a legislative response to the pre-1996 regime where arbitral awards were routinely set aside on grounds of error or impropriety. The Court’s reasoning that the Division Bench acted within its rights under Section 37 in correcting a jurisdictional overreach is both principled and consistent with precedents such as Associate Builders v. DDA and Ssangyong Engineering.

However, the case highlights a recurring interpretive tension in Indian arbitration law: when does a judicial error in applying Section 34 justify intervention under Section 37, and when does that intervention itself become appellate in nature? The fine line drawn by the Court here may set a precedent, but also underscores the need for clearer appellate guidelines under Section 37.

II. Liquidated Damages and the Doctrine of Waiver

The decision also revisits the legal and commercial implications of granting extensions of time in construction contracts. The appellant’s argument — that granting such extensions nullifies the employer’s right to damages — draws strength from traditional equitable doctrines such as waiver, estoppel, and election.

The Court’s rejection of this argument, based on the express “without prejudice” language used in the extension letters, is correct from a positivist contract law perspective. However, from a policy standpoint, this approach potentially reinforces imbalanced power dynamics in government contracts. When government agencies routinely reserve broad punitive powers even after accepting delayed performance, it may create an atmosphere of uncertain risk allocation, particularly for small and mid-size contractors.

Additionally, the Court missed an opportunity to elaborate on the evidentiary burden under Section 74 of the Contract Act — specifically, the extent to which the genuineness of the pre-estimate of loss must be demonstrated when liquidated damages are enforced. The arbitral tribunal's reliance on evidence of rent loss was accepted without examining whether this loss was proportionate to the damages levied — an area deserving deeper judicial guidance.

III. Arbitral Autonomy vs. Judicial Oversight: Is Balance Fully Achieved?

While the Supreme Court rightly defends arbitral autonomy as the cornerstone of the modern arbitral regime, its strong endorsement of non-interference might also discourage legitimate challenges even in cases where the arbitral reasoning is shallow or inadequately reasoned.

Indeed, Delhi Airport Metro Express v. DMRC and M. Hakeem have drawn similar lines, but none fully address the scenario where an award — though formally reasoned — fails to grapple with material contractual or factual anomalies. Thus, the Court’s position may be critiqued as reinforcing form over substance, and undermining the right to meaningful judicial review, especially when the award’s impact extends beyond the commercial realm into public funds, transparency, or infrastructure development.

IV. Implications for Arbitration Practice and Contract Drafting

This ruling has immediate doctrinal and practical consequences. First, arbitral tribunals may feel emboldened to adopt firm stances on contractual interpretation without fear of subsequent judicial review. Second, government departments and public sector undertakings (PSUs) will likely rely more heavily on "without prejudice" clauses to insulate themselves from liability while extending deadlines — reinforcing a risk-averse, rigid approach to public contracts.

For legal practitioners, the case underscores the need to draft clear and defensible clauses regarding time, compensation, and dispute resolution — and to maintain documented communications that can withstand arbitral and judicial scrutiny.

Conclusion

The Supreme Court’s judgment in Consolidated Construction Consortium Ltd. v. Software Technology Parks of India affirms and strengthens the jurisprudence favoring finality and autonomy in arbitration, while reiterating the limited scope of judicial interference under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996. By upholding the Division Bench's restoration of the arbitral award and rejecting the Single Judge’s overreach, the Court sent a clear message that arbitral decisions — even when contested — must be respected if they fall within a plausible interpretive and evidentiary framework.

Importantly, the judgment clarifies that granting extensions of time does not automatically invalidate the imposition of liquidated damages, particularly where the employer has consistently reserved its rights. It also demonstrates that Indian courts are increasingly aligned with international standards that discourage re-litigation of arbitral disputes under the guise of statutory review.

This decision is a valuable precedent for arbitration practitioners, contract drafters, and policymakers. It underscores the need for careful contract management, clear documentation of time extensions, and express reservation of rights during the performance of obligations. At a broader level, the judgment advances India’s goal of becoming an arbitration-friendly jurisdiction, reinforcing that the role of courts is supportive, not supervisory, in the arbitral process.

References

Primary Sources

  1. Consolidated Construction Consortium Ltd. v. Software Technology Parks of India, (2025) INSC 574 (Supreme Court of India).
  2. Arbitration and Conciliation Act, 1996 (as amended):
    • Section 34 – Application for setting aside arbitral award.
    • Section 37 – Appealable orders.
  3. Indian Contract Act, 1872:
    • Section 55 – Effect of failure to perform at time fixed in contract.
    • Section 73 – Compensation for loss or damage caused by breach of contract.
    • Section 74 – Compensation for breach of contract where penalty is stipulated.
  4. UNCITRAL Model Law on International Commercial Arbitration, 1985, with 2006 amendments – Basis for the Indian Arbitration Act.

Case Law (Indian Supreme Court)

  1. Associate Builders v. Delhi Development Authority, (2015) 3 SCC 49
    – Landmark judgment delineating the narrow scope of judicial interference under Section 34.
  2. ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705
    – Leading case on “public policy” and whether arbitral awards can be set aside on that basis.
  3. Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority of India, (2019) 15 SCC 131
    – Interprets the 2015 amendments to the Arbitration Act; clarifies “patent illegality.”
  4. Delhi Airport Metro Express Pvt. Ltd. v. Delhi Metro Rail Corporation Ltd., (2022) 1 SCC 131
    – Reiterates that arbitrator's view cannot be substituted by court even if erroneous.
  5. Project Director, NHAI v. M. Hakeem, (2021) 9 SCC 1
    – Held that courts cannot modify arbitral awards; only power is to set aside under strict grounds.
  6. McDermott International Inc. v. Burn Standard Co. Ltd., (2006) 11 SCC 181
    – On finality of arbitral awards and the principle that courts cannot reappreciate evidence.

Books and Commentaries

  1. Chitty on Contracts, 32nd Edition, Vol. I: General Principles, Sweet & Maxwell (2015).
    – Particularly relevant to the doctrines of time as essence, liquidated damages, and waiver.
  2. Avtar Singh, Law of Arbitration and Conciliation, 11th Ed. (2022), Eastern Book Company.
    – A leading Indian treatise on arbitration law.
  3. O.P. Malhotra & Indu Malhotra, The Law and Practice of Arbitration and Conciliation, 4th Ed. (2022).
    – In-depth Indian commentary on Sections 34 and 37, including international perspectives.
  4. Gary B. Born, International Commercial Arbitration, 3rd Ed. (2019), Kluwer Law International.
    – Comparative arbitration law principles influencing Indian jurisprudence.

Journals & Reports

  1. Law Commission of India, 246th Report on Amendments to the Arbitration and Conciliation Act, 1996 (August 2014).
    – Legislative background to the introduction of Section 34(2A) and emphasis on minimal court interference.
  2. UNICTRAL Analytical Commentary on Model Law (1985) – Commentary on Article 34 (analogous to Section 34 of the Indian Act).

Dr.Vandita Chahar 
(Asst. Professor ) , Jaipur National University , Jaipur

Post a Comment

Previous Post Next Post